By Seun Ibiyemi
The Transmission Company of Nigeria (TCN) has restored bulk electricity supply through its Kukwaba 132kV Transmission Substation in Abuja after an outage that lasted about 40 hours.
TCN announced that power supply was restored at 4:16 p.m. on Thursday, October 15, 2026, following an interruption that began at 12:24 a.m. on Wednesday, October 14.
According to the company, the outage resulted from the tripping of the 33kV feeder L36, while restoration was delayed by a faulty line circuit breaker.
TCN said its engineers successfully connected feeder L36 to feeder L34 to restore bulk electricity supply to the affected load centres served by the Abuja Electricity Distribution Company (AEDC).
READ ALSO:Yahaya Bello trial: Witness links ₦1.425bn forex transactions to Adaudu
The company listed the affected areas as Daba Estate, Police Barracks, Kuchigoro Community, Veritas Plastic Company, Idu, Paipe Village, Hala Rice Company, Rico Godo Feed Max Company, Chessboard Estate and Chinese Stone in the Saburi area.
With the restoration of bulk power, AEDC is expected to distribute electricity to customers in the affected communities.
TCN expressed appreciation to customers for their patience and understanding during the outage.